Progress
CLAYTON J. LLOYD INTERNATIONAL AIRPORT
REDEVELOPMENT PROGRAM
Phase 1 - Enabling Works - Complete:
MARCH 2024 UPDATE
-
Temporary Car Park - Accommodates displaced parking in the location of the new terminal. The car park will be integrated into the landside expansion associated with the new ATB construction.
-
Apron Expansion - Provides a safe parking area, power in-out for E190 aircraft, and as the first phase towards expanding/infilling apron up to the new ATB.
-
Partial Parallel Taxiway - Enabling the relocation of Cargo building and future apron infill.
Phase 2A - Cargo Building - Complete:
AUGUST 2024 UPDATE
-
Cargo Building Operating as a standalone facility
-
Cargo relocated from old facility to new facility storage bay
-
Signage Installation Complete
-
Furniture Installations Complete
-
Apron Commissioning In Progress
JULY 2024 UPDATE
-
Exterior/Interior Finishes Complete
-
HVAC, Plumbing & Electrical Complete
-
Landside Paving, and Security Gate Installation Complete
-
Signage Installation Ongoing
-
Furniture Assembled and Delivered to site
JUNE 2024 UPDATE
-
Majority of Exterior Finish installation Complete
-
Majority of Interior Finishes Complete (some minor touch-ups are required, one last coat of paint, floor polishing, and ceiling tiles once the electrical and HVAC is completed)
-
Majority of HVAC and Electrical Installations Complete
-
Exterior Doors, Windows and Shutters Installed
MAY 2024 UPDATE
-
Majority of Exterior Primer installation Complete
-
Interior Finishes ongoing – high bay ceiling has been painted, majority of tiles installed, washroom tiling/painting complete (just require fixtures and misc finishes), majority of drywalling complete
-
HVAC and Electrical installations ongoing
-
Landside kerb and sidewalks poured. Next will be ramps and steps
-
Site Services installations ongoing (no pictures here)
-
Enabling works on mahogany road complete (no pictures here unless you’d want them – most of the area is now backfilled)
APRIL 2024 UPDATE
-
New Cargo Building - All Cargo building roof slabs formed, poured, and cured. Exterior Wall Render Completed
-
New Cargo Apron - Airside and Landside Excavation ongoing (in preparation for apron)
-
New Carpark - Airside and Landside Excavation ongoing (in preparation for new parking lot)
-
New Service Road
-
Utility Works for the Air Terminal Building - Electrical Rough-Ins Completed
MARCH 2024 UPDATE
-
New cargo Building
-
New cargo Apron
-
New carpark
-
New Service Road
-
Utility Works for the Air Terminal Building
Phase 2B - Air Terminal Building - In-Progress:
MARCH 2025 UPDATE
-
All ground-floor concrete walls completed (poured)
-
Finalized masonry wall installations in the Arrivals baggage reclaim area
-
HVAC installations ongoing throughout Western third/section of the building
-
West side Mechanical & Electrical Rooms blockwork completed
-
Drywall stud and gypsum board installation ongoing in West Office areas
-
Departure hold area roof decking/scaffolding installations ongoing & roof slab pouring ongoing
-
Storm Pipe & Trench Drain Installation Ongoing (Majority of Airside STW scope complete)
-
Continued WWTP Installation. Blinding poured; foundation steel installed
-
Continued airside and landside lighting installations. Foundations poured; conduits routed
FEBRUARY 2025 UPDATE
-
All Floor Slabs completed (poured)
-
All roof slabs and inverted beam poured/completed from GL 8 – 14 (The Western third of the building).
-
Finalized masonry wall installations in the Arrivals baggage reclaim area, and continuing installations along on the West side of the building
-
HVAC installations ongoing throughout Western third/section of the building
-
Drywall stud installation started
-
Commenced Wastewater Treatment Plant Installation
-
Commenced Airside and Landside lighting installations
-
East side future parking lot caliche placed and compacted
JANUARY 2025 UPDATE
-
Contractor remobilized from Christmas Break
-
Eastern Cistern Backfilled and Substructure Works Complete
-
Continue installations of West superstructure walls and roofs.
-
Mezzanine Floor Slab Poured
-
Baggage Reclaim Roof Poured
-
Majority of Phase F-1 Apron works completed
-
Airside STW and outfall installation close to completion (minor works remain)
OCTOBER 2024 UPDATE
-
Majority of Substructure Completed (Only East Cistern and a few step footings remain)
-
All external Eastern Stormwater Cistern Wall Poured, once internal walls are poured, and external walls are cured we will begin the top slab (final steps of the substructure)
-
Continued installations of West superstructure walls, started forming SW structure roof slabs
-
Apron works Continued – 50% PCC apron pour completed
-
Begun airside STW and outfall installations during night shift (completion expected in coming weeks)
SEPTEMBER 2024 UPDATE
-
Majority of Substructure Completed
-
Majority of external Eastern Stormwater Cistern Wall Poured (1 Pour Remaining)
-
Commenced installations of West superstructure walls
-
Existing Cargo Facility Demolished
-
Apron works ongoing – first PCC apron pour completed, and majority of stormwater infrastructure installed on landside area
AUGUST 2024 UPDATE
-
Western Potable Water Cistern Poured
-
Eastern Stormwater Cistern Slab Wall reinforcing steel completed, wall form installation ongoing
-
Foundations/Column/Shear Keys Completed. Substructure Walls Ongoing
-
Phase 1B Airside Works ongoing – excavations complete, lean concrete base pouring ongoing.
JULY 2024 UPDATE
-
Half of Western Cistern Walls Poured
-
Eastern Cistern Slab Wall reinforcing steel installation close to completion
-
Foundations/Column/Shear Keys installations ongoing
-
Phase 1B Airside Works ongoing – excavations complete
JUNE 2024 UPDATE
-
Western Cistern Slab poured, and strength confirmed. Steel installation for walls ongoing
-
Eastern Cistern Slab poured
-
Foundations/Column/Shear Keys installations ongoing
-
Site fencing erected next to existing cargo building, to allow for Stormwater/Trench Drain Installations
MAY 2024 UPDATE
-
Gates/Fences fully installed (site is now fully enclosed).
-
Western Cistern excavated, blinding poured and steel installation ongoing.
-
Majority of Eastern Cistern Excavation Complete
-
Foundations/Column excavations ongoing
-
Aecon site fully mobilized.
APRIL 2024 UPDATE
-
New Air Terminal Building
-
Ground-breaking Ceremony & Beginning of Site Mobilization
-
Delivery of project material and equipment
-
Tree Relocations and Clearing of site vegetation and topsoil.
-
Construction of site fencing, pedestrian walkways, and parking lot improvements
-
-
Apron Expansion
-
New Airside Access Road
-
New Landside Parking Lot, Airport Roads, and Pedestrian Plaza
MARCH 2024 UPDATE
Phase 2B - Air Terminal Building - Commencing March 2024
-
New Air Terminal Building
-
Apron Expansion
-
New Airside Access Road
-
New Landside Parking Lot, Airport Roads and Pedestrian Plaza
Phase 3 - Runway Extension - Future Project
PHOTOS COMING SOON...
A Vision Supported by Global Partnerships

The transformation of Clayton J. Lloyd International Airport into a world-class facility is propelled by generous support from the UK International Program. This redevelopment is a testament to our commitment to enhancing our capabilities and ensuring that the airport remains a key hub for international travel. Our vision extends beyond expansion; it's about creating a legacy of connectivity and service excellence for generations to come.