Progress
CLAYTON J. LLOYD INTERNATIONAL AIRPORT
REDEVELOPMENT PROGRAM
Phase 1 - Enabling Works - Complete:
MARCH 2024 UPDATE
-
Temporary Car Park - Accommodates displaced parking in the location of the new terminal. The car park will be integrated into the landside expansion associated with the new ATB construction.
-
Apron Expansion - Provides a safe parking area, power in-out for E190 aircraft, and as the first phase towards expanding/infilling apron up to the new ATB.
-
Partial Parallel Taxiway - Enabling the relocation of Cargo building and future apron infill.
Phase 2A - Cargo Building - Complete:
AUGUST 2024 UPDATE
-
Cargo Building Operating as a standalone facility
-
Cargo relocated from old facility to new facility storage bay
-
Signage Installation Complete
-
Furniture Installations Complete
-
Apron Commissioning In Progress
JULY 2024 UPDATE
-
Exterior/Interior Finishes Complete
-
HVAC, Plumbing & Electrical Complete
-
Landside Paving, and Security Gate Installation Complete
-
Signage Installation Ongoing
-
Furniture Assembled and Delivered to site
JUNE 2024 UPDATE
-
Majority of Exterior Finish installation Complete
-
Majority of Interior Finishes Complete (some minor touch-ups are required, one last coat of paint, floor polishing, and ceiling tiles once the electrical and HVAC is completed)
-
Majority of HVAC and Electrical Installations Complete
-
Exterior Doors, Windows and Shutters Installed
MAY 2024 UPDATE
-
Majority of Exterior Primer installation Complete
-
Interior Finishes ongoing – high bay ceiling has been painted, majority of tiles installed, washroom tiling/painting complete (just require fixtures and misc finishes), majority of drywalling complete
-
HVAC and Electrical installations ongoing
-
Landside kerb and sidewalks poured. Next will be ramps and steps
-
Site Services installations ongoing (no pictures here)
-
Enabling works on mahogany road complete (no pictures here unless you’d want them – most of the area is now backfilled)
APRIL 2024 UPDATE
-
New Cargo Building - All Cargo building roof slabs formed, poured, and cured. Exterior Wall Render Completed
-
New Cargo Apron - Airside and Landside Excavation ongoing (in preparation for apron)
-
New Carpark - Airside and Landside Excavation ongoing (in preparation for new parking lot)
-
New Service Road
-
Utility Works for the Air Terminal Building - Electrical Rough-Ins Completed
MARCH 2024 UPDATE
-
New cargo Building
-
New cargo Apron
-
New carpark
-
New Service Road
-
Utility Works for the Air Terminal Building
Phase 2B - Air Terminal Building - In-Progress:
SEPTEMBER 2025 UPDATE
-
Only Check-in Hall Tiling Remaining. Majority of wall tiling complete.
-
Majority of Millwork installations completed. Only check-in hall and departure desks remain.
-
Exterior stucco installation complete.
-
Building wayfinding signage installation complete.
-
Baggage Handling System installations underway
-
Roof Membrane and thermal paint installation complete
-
Majority of phase 1 apron areas complete.
-
Ceiling installation in check in hall completed. Installation of speakers and lighting ongoing.
-
Taxi-stand shade structures, drop off road and parking lot complete. Focus is on completing the last portion of the plaza area.
-
East and West side of the building inspected and approved for energization (should see lights and HVAC on in most of the building by end of first week of October).
AUGUST 2025 UPDATE
-
Majority of floor tiling completed throughout building. Wall tiling installation commenced.
-
Majority of drywalling completed throughout building.
-
Stucco installation completed on roof and majority of first coat completed on exterior.
-
Commenced panel installations of final apron area
-
Ceiling installation in check in hall commenced
-
Majority of mechanical equipment installed in primary mechanical room
-
Majority of Plaza taxi stand steel shade structures installed
-
Mahogany tree road fully poured (only driveways/entrance lanes to taxiway and parking lot remain)
-
Commenced Landscaping scope/plantings
-
50% complete wastewater treatment plant installations (comms, sanitary lines, control room, holding tanks and lift station)
-
Building wayfinding signage scope commenced
JULY 2025 UPDATE
-
Drywall, painting, and tiling completed in West side of building (Sector C)
-
Roofing waterproofing system completed. Only reflex white paint is required to complete scope.
-
Majority of mechanical infrastructure installations complete throughout building (HVAC, Fire Suppression, STW Drainage, Plumbing)
-
Completed majority of stucco installations on roof
-
Commence exterior stucco and finishes installations
-
Commenced washroom finish installations (toilets, sinks, tiles, etc.)
-
Primary switchboard (DP-A) energized inside ATB electrical room
-
Majority of Mahogany Tree Road Concrete Pouring completed
-
Apron PCC lanes poured for areas ‘F-1’ and ‘F-2’ (One area remaining to complete phase 1 scope)
-
Airside light masts installation commenced (4 installed)
JUNE 2025 UPDATE
-
Completed all window installations
-
Completed all sliding door installations
-
Completed all internal door installations
-
Commenced Roof Waterproofing
-
Commenced Acoustic Tile Ceiling Installations
-
Airport Office Tiling Completed (moved works to Arrivals Immigration and Baggage Reclaim)
-
Commenced Bulkhead/Drywall Installations in Mezzanine
-
Commenced Mahogany Tree Road Concrete Pouring (Kerbs)
-
Commenced Taxi/Drop Off Road Concrete Installations
MAY 2025 UPDATE
-
Majority of windows (both internal and external) installed
-
Majority of external doors installed
-
Commenced installation of internal doors
-
Mechanical units ‘landed’ on roof
-
Majority of parking lot poured
-
Roof concrete pouring completed
-
Wastewater Treatment Plant Holding tank walls poured
-
Airport office drywall completed
-
Airport office tiling installation commenced
APRIL 2025 UPDATE
-
Commenced window installations (Completed exterior window installations for Airport offices)
-
Completed West side mechanical and electrical room finishes
-
Commenced installation of fire suppression systems on West side of building
-
Commenced installation of HVAC on east side of building, in airline offices
-
Check in hall high walls poured. Architectural structural steel installations ongoing
-
Commenced installation of exterior fixed canopies
-
Continued installation of roof decking and steel on East side of building. The roof is scheduled to be completed (fully poured) by first week of May
-
First run of Apron trench drain poured/installed
-
Majority of landside storm water outlet installations complete (one headwall remaining)
MARCH 2025 UPDATE
-
All ground-floor concrete walls completed (poured)
-
Finalized masonry wall installations in the Arrivals baggage reclaim area
-
HVAC installations ongoing throughout Western third/section of the building
-
West side Mechanical & Electrical Rooms blockwork completed
-
Drywall stud and gypsum board installation ongoing in West Office areas
-
Departure hold area roof decking/scaffolding installations ongoing & roof slab pouring ongoing
-
Storm Pipe & Trench Drain Installation Ongoing (Majority of Airside STW scope complete)
-
Continued WWTP Installation. Blinding poured; foundation steel installed
-
Continued airside and landside lighting installations. Foundations poured; conduits routed
FEBRUARY 2025 UPDATE
-
All Floor Slabs completed (poured)
-
All roof slabs and inverted beam poured/completed from GL 8 – 14 (The Western third of the building).
-
Finalized masonry wall installations in the Arrivals baggage reclaim area, and continuing installations along on the West side of the building
-
HVAC installations ongoing throughout Western third/section of the building
-
Drywall stud installation started
-
Commenced Wastewater Treatment Plant Installation
-
Commenced Airside and Landside lighting installations
-
East side future parking lot caliche placed and compacted
JANUARY 2025 UPDATE
-
Contractor remobilized from Christmas Break
-
Eastern Cistern Backfilled and Substructure Works Complete
-
Continue installations of West superstructure walls and roofs.
-
Mezzanine Floor Slab Poured
-
Baggage Reclaim Roof Poured
-
Majority of Phase F-1 Apron works completed
-
Airside STW and outfall installation close to completion (minor works remain)
OCTOBER 2024 UPDATE
-
Majority of Substructure Completed (Only East Cistern and a few step footings remain)
-
All external Eastern Stormwater Cistern Wall Poured, once internal walls are poured, and external walls are cured we will begin the top slab (final steps of the substructure)
-
Continued installations of West superstructure walls, started forming SW structure roof slabs
-
Apron works Continued – 50% PCC apron pour completed
-
Begun airside STW and outfall installations during night shift (completion expected in coming weeks)
SEPTEMBER 2024 UPDATE
-
Majority of Substructure Completed
-
Majority of external Eastern Stormwater Cistern Wall Poured (1 Pour Remaining)
-
Commenced installations of West superstructure walls
-
Existing Cargo Facility Demolished
-
Apron works ongoing – first PCC apron pour completed, and majority of stormwater infrastructure installed on landside area
AUGUST 2024 UPDATE
-
Western Potable Water Cistern Poured
-
Eastern Stormwater Cistern Slab Wall reinforcing steel completed, wall form installation ongoing
-
Foundations/Column/Shear Keys Completed. Substructure Walls Ongoing
-
Phase 1B Airside Works ongoing – excavations complete, lean concrete base pouring ongoing.
JULY 2024 UPDATE
-
Half of Western Cistern Walls Poured
-
Eastern Cistern Slab Wall reinforcing steel installation close to completion
-
Foundations/Column/Shear Keys installations ongoing
-
Phase 1B Airside Works ongoing – excavations complete
JUNE 2024 UPDATE
-
Western Cistern Slab poured, and strength confirmed. Steel installation for walls ongoing
-
Eastern Cistern Slab poured
-
Foundations/Column/Shear Keys installations ongoing
-
Site fencing erected next to existing cargo building, to allow for Stormwater/Trench Drain Installations
MAY 2024 UPDATE
-
Gates/Fences fully installed (site is now fully enclosed).
-
Western Cistern excavated, blinding poured and steel installation ongoing.
-
Majority of Eastern Cistern Excavation Complete
-
Foundations/Column excavations ongoing
-
Aecon site fully mobilized.
APRIL 2024 UPDATE
-
New Air Terminal Building
-
Ground-breaking Ceremony & Beginning of Site Mobilization
-
Delivery of project material and equipment
-
Tree Relocations and Clearing of site vegetation and topsoil.
-
Construction of site fencing, pedestrian walkways, and parking lot improvements
-
-
Apron Expansion
-
New Airside Access Road
-
New Landside Parking Lot, Airport Roads, and Pedestrian Plaza
MARCH 2024 UPDATE
Phase 2B - Air Terminal Building - Commencing March 2024
-
New Air Terminal Building
-
Apron Expansion
-
New Airside Access Road
-
New Landside Parking Lot, Airport Roads and Pedestrian Plaza
Phase 3 - Runway Extension - Future Project
PHOTOS COMING SOON...
A Vision Supported by Global Partnerships

The transformation of Clayton J. Lloyd International Airport into a world-class facility is propelled by generous support from the UK International Program. This redevelopment is a testament to our commitment to enhancing our capabilities and ensuring that the airport remains a key hub for international travel. Our vision extends beyond expansion; it's about creating a legacy of connectivity and service excellence for generations to come.